Pengurasan Saluran Enam Kelurahan di Kembangan Dimaksimalkan

Channel on Jalan Kartini Raya Normalized

Some 75 personnel under Central Jakarta Water Resources Sub-agency is normalizing a 900-meter long water channel on Jalan Kartini Raya, Sawah Besar 

The work progress has touched 60 percent

"The work progress has touched 60 percent," expressed Sawah Besar Sub-district Water Resources Executing Unit Head, Nanang Kusnandi, Wednesday (8/7).

Channel on Jalan Kalibata Utara II Normalized

The channel will be widened from 60 to 80 cm. To optimize it, heavy equipment has been sent to the location.

"It is targeted to be completed in the upcoming September," he stated.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye809 personTiyo Surya Sakti
  2. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye710 personNurito
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye708 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye646 personTiyo Surya Sakti
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye452 personDessy Suciati