Channel on Jalan Kartini Raya Normalized
access_time August 08 2019 04:08 PM remove_red_eye 722
Reported by Rezki Apriliya Iskandar | Translated by Nugroho Adibrata
Reported by Rezki Apriliya Iskandar | Translated by Nugroho Adibrata
Some 75 personnel under Central Jakarta Water Resources Sub-agency is normalizing a 900-meter long water channel on Jalan Kartini Raya, Sawah Besar
The work progress has touched 60 percent
"The work progress has touched 60 percent," expressed Sawah Besar Sub-district Water Resources Executing Unit Head, Nanang Kusnandi, Wednesday (8/7).
Channel on Jalan Kalibata Utara II NormalizedThe channel will be widened from 60 to 80 cm. To optimize it, heavy equipment has been sent to the location.
"It is targeted to be completed in the upcoming September," he stated.